Home-building costs rise at their fastest pace since 2022
Building a house in New Zealand cost 1.7% more in the September quarter than in the June quarter, the fastest quarterly rise since late 2022, according to property data firm Cotality’s construction cost index. Annual growth climbed from 3.5% in the June quarter to 4.8%.
If you’re planning a new build or a big renovation in 2027, those figures matter. Cotality Chief Property Economist Kelvin Davidson said builders have so far carried some of the increase themselves, but that’s starting to change.
“Builders have absorbed some cost increases, particularly where existing projects are covered by fixed-price contracts. However, pricing for upcoming work is beginning to rise,” Kelvin said.
Which materials are going up
Materials make up around 50% of Cotality’s construction cost index, and wages around 40%. Kelvin said the products rising in price include “petroleum-based plumbing inputs, PVC, sealants, roof and ceramic tiles, reinforcing products and structural steel.”
He said the shift could change some households’ plans. “For some households, the changing cost equation could influence the choice between undertaking a new build and purchasing an existing property,” Kelvin said.
More homes are being consented
Builders are getting busier. Stats NZ figures show 41,091 new homes were consented in the year to September 2026, up 18% on the year before.
Canterbury led the growth, with 8,906 new homes consented in the year, up 31%. The monthly picture was more mixed, with the seasonally adjusted number of new homes consented falling 7.9% in September.
What it means for your project
A fixed-price contract locks in the price of a build, which is why builders on existing fixed-price jobs have absorbed recent cost rises. If you’re getting quotes now, check whether the price is fixed or whether it includes provisional sums or escalation clauses that pass cost increases on to you.
Ask your builder which materials in your design are most exposed to rising prices, such as plumbing, tiles, roofing and steel. Allowing a contingency in your budget for price rises during the build gives you room if quotes for later stages come in higher.
Get several quotes and compare what each one includes, because a lower headline price may leave out items another builder has priced in. Under the Building Act, a residential building contract above a set minimum price must be written and dated, and your builder must give you information about the work before you sign.
The Act also writes warranties into every residential building contract. They include that the work will be carried out in a proper and competent manner and with reasonable care and skill, that building products will be suitable for their purpose and new unless the contract says otherwise, and that the work will be finished by the date in the contract or, if there isn’t one, within a reasonable time.
If you’re weighing up building against buying, compare the full cost of each option, including land, consents, any development contributions, and the time a build takes. Kelvin’s point is that rising construction costs are now part of that calculation.
Cotality publishes its construction cost index every quarter, and the next update will cover the December quarter.